What was announced for Kuta and Mandalika in 2026, and what has happened since
Of seven things announced for Kuta and Mandalika in 2026, one is in use and one is being built. The other five are still plans.
Checked 27 November 2026. This page rests on published reports, each listed at the end with the date we read it, and on two checks of our own, which are marked as ours. We have not visited these sites for this page. Jump to the sources.
We followed seven announcements through the local press this year, and added one older promise for scale. The table shows where each one stands on 27 November 2026.
| What | Stage | Date given | We look again |
|---|---|---|---|
| Six new investors for The Mandalika | Talk | None | 28 Feb 2027 |
| Hotel at Kuta Lama | Announced | Work from Dec 2026 | 15 Jan 2027 |
| The race in 2027 | Announced | 29 to 31 Oct 2027, provisional | 31 Mar 2027 |
| Seaplanes from Batujai Dam | Signed | First landing 17 Dec 2026, after an earlier target was missed | 31 Dec 2026 |
| Darwin flight | Announced | Feb or Mar 2026, passed | 11 Jan 2027 |
| Go-kart circuit | Started | Open in Dec 2026 | 15 Jan 2027 |
| Singapore and Kuala Lumpur flights | Finished | Added in Jun 2026 | With each month's arrivals |
| Rinjani cable car, from 2022 | Announced | Complete in 2025, passed | 15 May 2027 |
The last column is the date we next look at each one. What we find goes on this page under that item.
How we sort a headline
A headline rarely says how far along a project is, so we file each one under the furthest stage it has reached.
- Talk
- Someone has said they are interested, or a meeting took place. Nothing is signed and often nobody is named.
- Announced
- A named body has stated a plan, usually with a date.
- Signed
- There is an agreement on paper. Permits, land or money may still be missing.
- Started
- Work is under way on the ground, and the thing is not open yet.
- Finished
- It is open, on sale or in use.
Where a date was given and has gone by, the table says "passed" beside it. The item stays at the stage it had reached.
Five that are still plans
None of these five is built. Each rests on a statement reported in the local press: by ITDC's managers, by provincial officials, by the race promoter and by a hotel association. The first sentence of each item says who reported it and when.
Six new investors, about Rp 4 trillion
Suara NTB reported on 16 November 2026 that six new investors had stated their interest in The Mandalika this year, worth about Rp 4 trillion. The speaker was the general manager of The Mandalika, the resort zone run by the state company ITDC. He named no investor, so there is nothing yet for you to check, and a name is the first thing to ask for. He said the newcomers will build once the land is ready, described its legal status as settled, and put the delay down to the dozens of residents who still live and trade there. He hoped to have the land prepared by the end of the year.
Three weeks earlier an ITDC director had put investment commitments at about Rp 3.7 trillion (Suara NTB, 28 October 2026). The two figures may not count the same thing.
A hotel of about 132 rooms at Kuta Lama
Lombok Post reported on 13 November 2026 that ITDC plans to reshape Kuta Lama, the old beachfront strip in Kuta, in stages. The first stage is a hotel of about 132 rooms with a convention centre, and ITDC has scheduled work to begin in December. The report names no permit and no contractor.
Three more reports followed within a fortnight. State radio said talks with residents were still to come, and that a place at Bazaar Mandalika was one option for the strip's traders (RRI Mataram, 13 November). The deputy regent asked ITDC to explain the plan more widely (Lombok Post, 14 November). A senior regency adviser asked that traders stay where they are until building is certain, and recalled an investment of about Rp 2 trillion once promised for Tanjung Aan which, he said, never arrived. He supports tidying the strip (Lombok Post, 25 November).
The race in 2027, and the years after
The race promoter's provisional calendar puts the 2027 Indonesian round at Mandalika on 29 to 31 October 2027, as Suara NTB reported on 27 September 2026. The calendar is provisional, so the date can change.
Beyond 2027 there is only talk. The chair of the provincial hotel and restaurant association asked the government in October to extend the race contract. She said the promoter had signalled its support to 2031 and the government had not confirmed (Suara NTB, 20 October 2026). That report does not give the end date of the present contract, and we look for it on 28 February 2027.
The 2026 race weekend is the measured part: 157,875 visitors over three days, up from 140,324 in 2025, by the organisers' count (Antara, 12 October 2026). A visitor who came on each of the three days counts three times.
Seaplanes from Batujai Dam
Suara NTB reported on 27 September 2026 that a cooperation agreement for seaplane flights from Batujai Dam in Central Lombok was signed on 31 August. The head of the provincial transport office gave the date and did not name the parties. The plan starts with about four aircraft of about 14 seats each.
Kicknews reported on 22 October 2026 that the province had hoped in June for a first flight in late July or early August, which did not happen. In September the permit to use the dam and the permits to fly were still in process, and the old jetty needed work. The province's new date is a first landing on 17 December 2026, with the public works ministry's permit for the dam still outstanding.
A direct flight to Darwin
TransNusa announced a Darwin to Lombok flight in January 2026, for February or March (Karryon, 27 January 2026). That date passed. The governor said on 15 February that the route could open that month if nothing stood in the way, and on 10 June that it was still waiting for its licence (Republika, 15 February 2026; Antara, 10 June 2026).
A report of 20 November on the province's visitor numbers lists Darwin among the routes airlines have opened or added (NTBSatu, 20 November 2026). Our own check, on 27 November 2026, was a search for a first flight or a schedule, and it found neither.
Two on the ground
A go-kart circuit beside the race track
Suara NTB reported on 28 October 2026 that a private company is building a go-kart circuit of about two hectares, with a track of about one kilometre, east of the Mandalika circuit. ITDC's operations director said building was continuing and gave December 2026 for the opening.
More flights from Singapore and Kuala Lumpur
Scoot went from four flights a week between Singapore and Lombok to ten in June 2026, the airport's general manager said (detikBali and RRI, 9 June 2026), and Lion Air announced a daily flight from Kuala Lumpur from 28 June (Lion Air, 15 June 2026). The provincial statistics office, BPS Nusa Tenggara Barat, reported passengers arriving direct from both cities in September, so both routes were flying then (Radar Lombok, 3 November 2026). Our own check on 21 November 2026 found no third scheduled international destination.
BPS counted 9,039 direct foreign arrivals at the airport in July 2026, 12.11 percent below July 2025, and 7,657 in September, 17.96 percent below September 2025. July's figure was reported on 1 September 2026 and September's was released on 2 November 2026. We have no year-on-year figure for August, and two months is too short a run to say what the extra flights have done. The monthly figures are in our guide to the visitor statistics.
One older promise, for scale
The Rinjani cable car
CNN Indonesia reported on 18 December 2022 that the first stone had been laid for a cable car from Karang Sidemen village in Central Lombok towards Mount Rinjani, with completion projected for 2025. That date passed. On 6 May 2026 the head of the province's environment and forestry office said the project was still in its environmental assessment, which sits with the central government (Antara, as carried by Metro TV). We file a first-stone ceremony under announced, because no building followed it.
If you are buying
Nothing on this page values a plot or a villa. When someone quotes you one of these headlines beside a property, we would ask three things.
- Which stage is it at, and who says so?
- What date was given, and has it passed?
- Does the price or the rental projection you were shown assume it? Ask to see the numbers without it.
What we have not read, and what you can do
- We have not read any agreement, permit or contract named here. If one of them matters to your purchase, ask the person who quotes it to show you the document.
- ITDC's own press page listed no release on Kuta Lama or the six investors when we read it on 27 November 2026, so both rest on what its managers said to reporters. A release or a permit number is what would move either up a stage.
- We could not confirm the Darwin route's status with the airline. You can test it yourself by trying to book a seat.
Sources
- Suara NTB, 16 November 2026, on the six investors and the land at Kuta Lama: suarantb.com. Read 27 November 2026.
- Lombok Post, 13 November 2026, on the Kuta Lama plan: lombokpost.jawapos.com; 14 November, the deputy regent: lombokpost.jawapos.com; 25 November, the regency adviser: lombokpost.jawapos.com. Read 27 November 2026.
- RRI Mataram, 13 November 2026, on talks with residents: rri.co.id. Read 27 November 2026.
- Suara NTB, 27 September 2026, on the 2027 calendar: suarantb.com; 20 October 2026, on the contract: suarantb.com. Read 27 November 2026. Race attendance: Antara, 12 October 2026, read 22 November 2026.
- Suara NTB, 27 September 2026, on the seaplanes: suarantb.com. Kicknews, 22 October 2026: kicknews.today. Read 27 November 2026.
- Suara NTB, 28 October 2026, on the go-kart circuit and the Rp 3.7 trillion figure: suarantb.com. Read 27 November 2026.
- Flights from Singapore and Kuala Lumpur, and direct foreign arrivals: the sources are listed in our guide to the visitor statistics, checked 21 November 2026. Passengers arriving direct from both cities in September 2026: the head of the provincial statistics office, as reported by Radar Lombok, 3 November 2026. Read 27 November 2026.
- The Darwin route: Karryon, 27 January 2026, and Antara, 10 June 2026, as listed in our statistics guide and checked 21 November 2026. Republika, 15 February 2026: republika.co.id. NTBSatu, 20 November 2026: ntbsatu.com. Both read 27 November 2026.
- CNN Indonesia, 18 December 2022, on the cable car: cnnindonesia.com. Metro TV, carrying Antara, 6 May 2026: metrotvnews.com. Read 27 November 2026.
- ITDC press page, read 27 November 2026: itdc.co.id.
General information, not investment advice. Plans are reported as plans. Dates and figures are those stated by the source named beside them, and nothing here is a projection of what will be built or of what any property would earn.